If you have any question about ATM Study Solutions exam software or other exam materials, or any problem about how to purchase our products, you can contact our online customer service directly. Besides, during one year after you purchased our ATM Study Solutions exam software, any update of ATM Study Solutions exam software will be sent to your mailbox the first time. As a reliable company providing professional IT certificate exam materials, we not only provide quality guaranteed products for ATM Study Solutions exam software, but also offer high quality pre-sale and after-sale service. By adding all important points into practice materials with attached services supporting your access of the newest and trendiest knowledge, our ATM Study Solutions preparation materials are quite suitable for you right now as long as you want to pass the ATM Study Solutions exam as soon as possible and with a 100% pass guarantee. Our ATM Study Solutions study questions are so popular that everyday there are numerous of our loyal customers wrote to inform and thank us that they passed their exams for our exam braindumps. Our Shobhadoshi technical team have developed the ATM Study Solutions exam review materials in accordance with the memory learning design concept, which will relieve your pressure from the preparation for ATM Study Solutions exam with scientific methods.
Despite the intricate nominal concepts, ATM - Advanced Test Management Exam v3.0 - ISTQB Study Solutions exam dumps questions have been streamlined to the level of average candidates, pretense no obstacles in accepting the various ideas. What most useful is that PDF format of our Valid ATM Soft Simulations exam materials can be printed easily, you can learn it everywhere and every time you like. It is really convenient for candidates who are busy to prepare the exam.
Shobhadoshi is the best platform, which offers braindumps for ATM Study Solutions Certification exam duly prepared by experts. Our ATM Study Solutions exam material is good to ATM Study Solutions pass exam in a week. Now you can become ATM Study Solutionscertified professional with Dumps preparation material.
With many advantages such as immediate download, simulation before the real exam as well as high degree of privacy, our ATM Study Solutions actual exam survives all the ordeals throughout its development and remains one of the best choices for those in preparation for ATM Study Solutions exam. Many people have gained good grades after using our ATM Study Solutions real dumps, so you will also enjoy the good results. Don’t hesitate any more. Time and tide wait for no man. Come and buy our ATM Study Solutions exam questions!
However, how to pass ISTQB certification ATM Study Solutions exam quickly and simply? Our Shobhadoshi can always help you solve this problem quickly. In Shobhadoshi we provide the ATM Study Solutions certification exam training tools to help you pass the exam successfully.
QUESTION NO: 1
During the system testing phase a tester from your test team observes a failure in the system under test and he/she decides to create an incident report. The incident report is currently in a "new" state, indicating it needs to be investigated.
Which THREE of the following information items can't yet be present in the incident report?
K3 2 credits (2 credits out of 3 credits correct, 1 credit point)
A. Steps to reproduce the failure, including screenshots, database dumps and logs where applicable
B. What really caused the failure (actual cause)
C. The lifecycle phase in which the defect has been introduced
D. The actual and the expected result highlighting the failure
E. The type of defect that caused the failure
Answer: B,C,E
QUESTION NO: 2
Which of the following statements best describes an appropriate approach for managing exploratory testing?
Number of correct responses: 1
K2 1 credit
A. Exploratory testing should not be managed because such testing is inherently unmanageable and not measurable
B. Define very detailed mission statements, which allow testing work to be broken into sessions of up to 10 minutes duration in which testing is guided by these mission statements
C. Break the testing work in 30 to 120 minutes sessions and use properly defined mission statements consisting of two or three sentences to guide testing during these sessions
D. Define very generic charters to drive exploratory testing sessions of 2 days where testers are completely free to decide what to test
Answer: C
QUESTION NO: 3
You are managing the system testing for a SOA based system. The integrated system consists of several subsystems:
- A SOA middleware
- A CRM (Customer Relationship Management) system
- A BRM (Billing and Revenue Management) system
- A SMS (Subscriber Management System) system and you performed a risk analysis based on these subsystems.
At the end of the scheduled period for test execution you produce a first classical report based on the traditional metrics of testing. Test pass/fail status and bug status
(open/resolved) That table provides you a distorted picture of the quality risk, because there is no indication of the risk level of the failed tests, the tests not run, or the open bugs.
Thus, you produce the following table to solve this distortion issue:
In the table above, where you have introduced the concept of risk weighting, the highest risk test or bug report has a score of 1, while the lowest risk test or bug report has a score of 0.04.
Which of the following subsystems, based on the risk scores of the table, is most risky?
K4 3 credits
A. BRM
B. SOA
C. CRM
D. SMS
Answer: C
QUESTION NO: 4
Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
K2 1 credit
A. Test reporting activities are still important with an iterative lifecycle. The reports can be used to conduct post-iteration review sessions before starting with the next iteration
B. Test reporting activities are not important for projects adopting an iterative lifecycle model with short iterations
C. Test reporting activities can't be influenced by the use of an iterative lifecycle model with short iterations
D. Test reporting activities are less important for projects adopting an iterative life cycle model with short iterations. They should be performed at the end of the last iteration
Answer: A
QUESTION NO: 5
In the test strategy document your organization declares:
- To adopt a V-model development lifecycle, with three formal levels of testinG. unit, integration and system testing
- To use a blended risk-based and regression-averse testing strategy for each level of testing
The following is an excerpt of the "approach" section for the system test plan document of a new project:
"Testing will only use manual tests. Due to the short period of time for test execution, the following activities will be performed in parallel with test execution: Test planning, test analysis and test design.
Basic metrics will be taken for test effort (i.e. person-hours), test cases executed
(passed/failed), and incidents (no more metrics, such as code coverage, will be collected)."
In the system test plan, no deviations from the test strategy are described.
Based only on the given information, which of the following statements is true?
K4 3 credits
A. The approach described the system test plan document is inconsistent with both the risk-based and regression testing strategies
B. The approach described in the system test plan document is consistent with the test strategy
C. The approach described in the system test plan document is consistent with the risk- based testing strategy, but it is inconsistent with the regression testing strategy
D. The approach described in the system test plan document is consistent with the regression testing strategy, but it is inconsistent with the risk-based testing strategy
Answer: A
To pass the exam in limited time, you will find it as a piece of cake with the help of our Microsoft MB-280 study engine! Psychiatric Rehabilitation Association CFRP - Through so many feedbacks of these products, our Shobhadoshi products prove to be trusted. They are abundant and effective enough to supply your needs of the Microsoft SC-300 exam. ISC CISSP-KR - If you fail to pass the exam, Shobhadoshi will full refund to you. SAP C_HRHFC_2411 - Besides, you can take notes on it whenever you think of something important.
Updated: May 25, 2022
Exam Code: ATM
Exam Name: Advanced Test Management Exam v3.0 - ISTQB
Updated: June 13, 2025
Total Q&As:52
ISTQB New ATM Test Questions
Free Download
Exam Code: ATM
Exam Name: Advanced Test Management Exam v3.0 - ISTQB
Updated: June 13, 2025
Total Q&As:52
ISTQB Exam ATM Tutorials
Free Download
Exam Code: ATM
Exam Name: Advanced Test Management Exam v3.0 - ISTQB
Updated: June 13, 2025
Total Q&As:52
ISTQB Valid Practice Questions ATM Files
Free Download